We discovered our new house to be in mid-June the weekend I returned from New Zealand. We put it under contract on July 18, 2011.
Here is a summary list of the blogs Pre-Contract and at the midway point under contract, from early July 2011 up through mid-August 2011:
Pre-Contract
1. Our Dream Home: We Got It!
2. How did we get our dream home?
3. Why did the builder split the existing structure into 2 residences?
4. Why did Alan fall in love with this house?
5. What design ideas did our realtor suggest for the bathroom?
6. How did the builder design the kitchen?
7. When did I start taking a HUGE number of snapshots of the house?
8. Which friends and relatives saw the house first?
9. What is the one thing I really liked about the house early on?
10. During the remodel process, which room did I enjoy seeing the most?
11. What did Alan want removed from the office?
12. In which room did the builder fill in the most windows?
13. Which room makes the house feel like a tree house?
14. When and Why did we hire an Interior Decorator?
First Week Under Contract
15. On what date did we put an official contract on the house?
16. What were 3 major interior design decisions the 1st week under contract?
17. What color did I want for the exterior of the house?
18. What did the exterior of the house look like the 1st week under contract?
19. Whose window trim and baseboard trim did I copy?
20. What does the builder love to provide in each remodel?
21. Which building material did the builder use for all the interior trim?
22. How are the two sun porches coming along?
Second Week Under Contract
23. What surprised me the most the 2nd week under contract?
24. Let the paint experimentation begin
25. The granite and an old door are installed
26. The additional arch
27. The unsexy things that make a house better constructed
28. Bring on the sample testing of the green exterior paint
29. Interior wall color: I got my gray
30. Character and more character: What Lies Beneath
31. The Entertainment Center is built
32. The kitchen and bathroom tile are installed
33. The sun porch floor tile is installed
Third Week Under Contract
34. How did the 3rd week under contract start?
35. The dog doors are installed
36. The laundry room tile and drain are installed
37. Taping for painting
38. The area between the front planter and house is made less permeable
39. Selecting a fence stain color
40. What color should the attic vent be?
41. The interior trim color is sprayed on
Fourth Week Under Contract
42. The plywood ramp is removed and the sprinkler system is being installed
43. I see gray paint
44. The gray stone dining room wall
45. Scoping out house numbers in the new hood
46. The bathroom fixtures are installed
47. The nails are puttied and I notice the crawl space
48. The master bedroom fire alarm and ceiling fan are installed
49. More ceiling fans are installed
50. The house exterior is being primed
51. The kitchen sink, faucet, and soap dispenser are installed
52. I see the hardwood floor again
53. I see Pistachio green
54. Navy pops into my head


March 26, 2012







